Activity2: Item rates for installation & commissioning of transformer
Installation & Commissioning of 315 KVA dry type
transformer 
Schedule of quantity
Note: This schedule of quantity is for providing an idea regarding item specifications during the execution of the above work. Rates are subjected to vary from time to time. 
| 
   
Sl. 
No. 
 | 
  
   
Description of item 
 | 
  
   
Unit 
 | 
  
   
Quantity 
 | 
  
   
Rate 
 (Rs) 
 | 
  
   
Amount 
(Rs.) 
 | 
 
| 
   
1 
 | 
  
   
Removal of transformer yard fencing by carefully removing the nut
  bolts etc., Decommissioning of the existing 630 KVA, 11/0.4 kV oil
  transformer and shifting of transformer from the platform to the safe area within
  substation according the instructions of engineer in charge. 
 | 
  
   
job 
 | 
  
   
1 
 | 
  
   
7,500/- 
 | 
  
   
7,500/- 
 | 
 
| 
   
2 
 | 
  
   
Shifting of the 315 KVA, 11KV/433 V Cast Resin Dry type transformer
  from substation area to platform including locking of transformer wheels and
  re-fixing the fencing to original condition etc as directed by the engineer
  incharge. 
 | 
  
   
job 
 | 
  
   
1 
 | 
  
   
5,000/- 
 | 
  
   
5,000/- 
 | 
 
| 
   
3 
 | 
  
   
Installation & commissioning of new 315 KVA Cast Resin Dry type
  transformer in accordance with IS 10028 - Code of practice for Installation
  & maintenance of transformer including Pre commissioning tests and
  earthing of neutral and body of transformer etc. complete as directed by the
  engineer incharge.. 
 | 
  
   
job 
 | 
  
   
1 
 | 
  
   
20,000/- 
 | 
  
   
20,000/- 
 | 
 
| 
   
4 
 | 
  
   
Arrangement of temporary power supply during changing of transformer.
  (630 KVA transformer with a load demand of 240 KVA) 
 | 
  
   
Day 
 | 
  
   
3 
 | 
  
   
3,000/- 
 | 
  
   
9,000/- 
 | 
 
| 
   | 
  
   
Total  
 | 
  
   
41,500/- 
 | 
 |||