Activity 5: Schedule of quantity for the work "Replacement of LT Panel"
Name of
work: Replacement of LT electrical panel.
Schedule of quantity
Sl. No. 
 | 
  
Description
  of item 
 | 
  
Unit 
 | 
  
Quantity 
 | 
  
Rate (Rs.) 
 | 
  
Amount
  (Rs.) 
 | 
 
1 
 | 
  
Decommissioning & dismantling of the
  existing 415V, 1200 amps, main LT panel  and sub panel totally
  and shifting it to a suitable location in Electrical sub-station as per the
  directions of engineer-in-charge. The work also includes minor civil works, disconnection
  of all the incoming cables and outgoing cables from the existing LT panel,
  cleaning the trenches together with cost of labour, transport, tools
  &plants, stacking of serviceable materials complete. 
 | 
  
Lump sum 
 | 
  
1 job 
 | 
  
50000.00 
 | 
  
50000.00 
 | 
 
2 
 | 
  
Supply, erection, testing & commissioning
  of indoor type Main LT Panel, floor mounting type, dust and vermin proof by
  construction of 14 SWG CRCA sheets compartmentalized, modular type IP42
  protection with powder coated panel        
   (followed by seven/ eight tank
  process) confirming to the technical specifications of Annexure-II including
  heavy duty terminal blocks, neoprene rubber gaskets for joints, anodized
  aluminum name plates for incoming and outgoing cables, enameled danger boards
  by connecting all incoming & outgoing cables (end terminations of all
  cables as a separate item No.3 below) all complete together with the required
  minor civil works, cost of material, labour, transport, taxes, tools &
  plants and as per the specifications and directions of engineer-in-charge. 
Incomer: 
1.    1000A, four pole on load change over switch. 
2.    1000A TP ACB 50 KA EDO with microprocessor
  based earth fault/ Over current/ Short Circuit relays with shunt trip coil (confirming
  to specifications of annexure-I) 
Metering & Indication: 
1.    Current transformer rated 1000/500/5A,
  10VA, Cl 1.0 for metering. 
2.   Digital multi data meter Cl 0.5 with RS 485. 
3.   LED Type RYB indication lamps, On/Off/Trip
  Indication lamps with control MCBS/Circuits. 
4.   2 Nos. of suitable Cl 0.5 Trivector meters
  with RS 485 for main supply and Generator supply. 
Bus Bars: 
1.    1000TPN Aluminum Bus bars.        
Current density should not exceed 1A per Sq.mm.
  Heat shrinkable sleeves & SMC Supports shall be provided to the bus bar 
Outgoing: 
1.    2Nos-400A 36KA TP MCCB  
2.    4Nos-200A 36KA TP MCCB 
3.    4Nos-100A 25 KA TP MCCB 
4.    2Nos-63A 25KA TP MCCB 
Note: 1. LT
  panel should properly accommodate all the incoming and outgoing cables as
  detailed in Diagram2. 
2.   
  GA diagram of LT panel shall be approved
  from the department. 
3.  
  Installation and commissioning of LT panel
  shall be done within 12 hours only. 
(ACB Specification should be mentioned in Annexure-I & LT panel specifications should be mentioned in Annexure-II) 
 | 
  
Lumpsum 
 | 
  
1 job 
 | 
  
950000.00 
 | 
  
950000.00 
 | 
 
3 
 | 
  
End terminations of 1.1KV, 3.5 core/3 core,
  XLPE /PVC  aluminum conductor cable
  along with the jointing materials such as heavy duty crimping type lugs,
  cable glands, HT tapes etc., complete with the cost of jointing materials, labour
  tools & implements & as per the direction of Engineer-In-Charge. 
 | 
  ||||
a.    
  300 Sq.mm 
 | 
  
Each 
 | 
  
2 Nos. 
 | 
  
4000.00 
 | 
  
8000.00 
 | 
 |
b.    240 Sq.mm 
 | 
  
Each 
 | 
  
4 Nos. 
 | 
  
4000.00 
 | 
  
16000.00 
 | 
 |
c.    185 Sq.mm 
 | 
  
Each 
 | 
  
3 Nos. 
 | 
  
3000.00 
 | 
  
9000.00 
 | 
 |
d.           
  70 sq.mm 
 | 
  
Each 
 | 
  
2 Nos. 
 | 
  
2500.00 
 | 
  
5000.00 
 | 
 |
e.    25 sq.mm 
 | 
  
Each  
 | 
  
3  Nos. 
 | 
  
2000.00 
 | 
  
6000.00 
 | 
 |
f.     10 sq.mm 
 | 
  
Each 
 | 
  
2 Nos. 
 | 
  
1000.00 
 | 
  
2000.00 
 | 
 |
4 
 | 
  
Buy-back offer for the existing 415V, 1200
  amps, 30 MVA capacity, draw out type "English electricals" make M-Pact
  Air Circuit Breaker & LT Panels on where is as is basis. The contractor has
  to lift the ACB & LT Panels at his own cost and risk and the amount thus
  quoted for taking back the ACB will be deducted/ adjusted against the bill
  for other items.( It is compulsory to quote this item also) 
 | 
  
Lump sum 
 | 
  
1 No 
 | 
  
-10000.00 
 | 
  
-10000.00 
 | 
 
Grand Total = ( 1 + 2+ 3 -4) 
 | 
  
1036000 
 | 
 
(Rupees ten
lakh thirty six thousand only)
(Engineer-In-Charge)