Activity2: Item rates for installation & commissioning of transformer
Installation & Commissioning of 315 KVA dry type
transformer
Schedule of quantity
Note: This schedule of quantity is for providing an idea regarding item specifications during the execution of the above work. Rates are subjected to vary from time to time.
Sl.
No.
|
Description of item
|
Unit
|
Quantity
|
Rate
(Rs)
|
Amount
(Rs.)
|
1
|
Removal of transformer yard fencing by carefully removing the nut
bolts etc., Decommissioning of the existing 630 KVA, 11/0.4 kV oil
transformer and shifting of transformer from the platform to the safe area within
substation according the instructions of engineer in charge.
|
job
|
1
|
7,500/-
|
7,500/-
|
2
|
Shifting of the 315 KVA, 11KV/433 V Cast Resin Dry type transformer
from substation area to platform including locking of transformer wheels and
re-fixing the fencing to original condition etc as directed by the engineer
incharge.
|
job
|
1
|
5,000/-
|
5,000/-
|
3
|
Installation & commissioning of new 315 KVA Cast Resin Dry type
transformer in accordance with IS 10028 - Code of practice for Installation
& maintenance of transformer including Pre commissioning tests and
earthing of neutral and body of transformer etc. complete as directed by the
engineer incharge..
|
job
|
1
|
20,000/-
|
20,000/-
|
4
|
Arrangement of temporary power supply during changing of transformer.
(630 KVA transformer with a load demand of 240 KVA)
|
Day
|
3
|
3,000/-
|
9,000/-
|
|
Total
|
41,500/-
|